Home

Description

PlovdivSvilengradRailway_ProjectSection.pdf (~ 130KB)

Technical Parameters

  • Project Length – approx. 150 Km
  • Approx. 20 Km Double Track
  • Maximum Speed - 160 km/hr for conventional trains and 200 km/hr for tilting trains
  • Standard UIC Gauge – 1435 mm
  • Rails – UIC 60
  • Sections implemented for future doubling
  • ‘Classic’ Single Phase 25 Kv AC 50 Hz OHL
  • 27 Stations & Halts – New Build / Rehabilitation
  • Connection to 110 Kv National Power Supply – 8 Overhead Lines
  • Traction Power sub-stations 110/25 kV – 4 nr. 
  • Extensive Structures – Bridges, Underpasses, Culverts Etc.
  • Signaling System (ETCS Level 1) – 252 km
  • Telecommunications – 252 km  

For the purposes of the project implementation, the following contracts have been signed:

  • 14.06.2005 Design and Build Contract for Civil, Track and Electrification Works for Phase 1: Krumovo - Parvomai between MTITC and TERNA S.A 
  • 22.08.2005 Technical Assistance to the Project management and Implementation Unit within NRIC for complex project management
  • 25.04.2006 Technical Assistance for the Supervision of the Whole Line between MTITC and Consortium Tecnica y Proyectos S.A, Louis Berger SAS, Systra S.A, TRADEMCO S.A and Rubicon Engineering Ltd
  • 05.09.2007 Design and Build Contract for Civil, Track and Electrification Works for Phase 2: Parvomai – Svilengrad – Turkish / Greek Borders between MTITC and ASTALDI S.p.A.
  • 05.09.2007 Signalling, Telecommunication and SCADA Systems for the Whole Line between MTITC and Consortium: Thales - Alacatel Luscent
  • 25.05.2009 Design and Build Contract for Civil, Track and Electrification Works for Phase 3: Svilebgrad - Turkish border between NRIC and OHL ZS s.a. between NRIC and OHL ZS s.a.
  • 29.12.2012 Additional Agreement 4/29.12.2012 to Contract for provision of technical assistance to PMIU at SE NRIC at complex contract management with ADO & WSP
  • 24.10.2011 Contract 3790 for raising of the alignment of the railway line and sccompanying additional works between NRIC and OHL ZS s.a.
  • 19.01.2012 Design and Built Contract 3888 ‘Dimitrovgrad – Harmanli railway section upgrading and electrification (from km 231+560 in the inter-station block Yabalkovo – Dimitrovgrad to km 266+000 in the inter-station block  Simeonovgrad - Harmanli), including Dimitrovgrad and Simonovgrad stations and all stations and halts between them, with approximate railway track length of 36 km’ signed between NRIC and  TERNA S.A.
  • 19.01.2012 Design and Built Contract 3889 ‘Harmanli – Svilengrad railway section upgrading and electrification (from km 266+000 in the inter-station block Simeonovgrad - Harmanli to km 297+750 in the inter-station block  Svilengrad – Turkish Border), including Harmanli and Svilengrad stations and all stations and halts between them, with approximate railway track length of 34 km and Svilengrad – Greek border railway upgrading and electrification with approximate length of 4 km’ signed between NRIC and JV Railway Infrastructure 2011 (PORR & PST Holding)
  • 19.01.2012 Design and Built Contract 3890 ‘Construction of new traction power substations in Simeonovgrad and Svilengrad and upgrading of the existing traction power substation in Dimitrovgrad’ between NRIC and Start Engineering
  • 04.09.2014 Contract 4732 „Additional Services under project BG161PO004-1.0.01-0005 “Plovdiv - Svilengrad Railway Electrification and Upgrading of Corridors IV and IX, Phase 2: section Parvomai-Svilengrad’’; Execution of independent construction supervision and Engineer under FIDIC until completion of the Project.”

WORKS CONTRACTS SUMMARY

   Phase1  Phase2  Phase3 Systems 
Contractor  TERNA  ASTALDI    THALES   ALCATEL
Base Country  Greece Greece  Italy Italy  Czech Republic
Austria Austria   Roumania Romania
Contract Value

99,792,441 Eur

68,000,000 Eur

69,999,666.00 BGN

35,557,047 Eur 

Commerncement

25 May 2006

2 October 2007

1 July 2009

16 October 2007

Duration

67 Months

49 Months

39 Months

109 Months

Completion

31 December 2011

9 November 2011

10 October 2012

28 November 2016

Project Length

37,7 Km

29,26 Km

17 Km

154 Km

 

   Phase 4.1  Phase 4.2  Phase 4.3

 Contractor

      

 Base Country

  Greece

Austria Austria    Bulgaria

  Bulgaria

 Contract Value

 136,000,000 BGN

 116,497,477.58 BGN

 20,350,493.36 BGN

 Commerncement

 15 February 2012

 15 February 2012

 15 February 2012

 Duration

 57 Months

 49 Months

 57 Months

 Completion

 16 November 2016

 15 March 2016

 18 November 2016

 Project Length

 34.44 Km

 35.75 Km

 -

 

SUPERVISION CONTRACT SUMMARY

Consortium of 5 Partners

  •  TYPSA (Lead)
  •  Spain
  •  SYSTRA
  •  France
  •  Louis Berger
  •  France
  •  Trademco
  •  Greece
  •  Rubicon Engineering
  •  Bulgaria
Contract Value – Eur 18,866,025
Contract Duration - 104 Months (to END OF 2014)

 

SUMMARY OF THE LONG-TERM TECHNICAL ASSISTANCE CONTRACT

Consortium between two partners

  •  ADO S.A.
  •  Greece
  •  WSP International Sweden
  •  Sweden

Contract Value – Eur 2,594,590
Contract Duration - 102 Months

 

 

 

employer

beneficiary

Engineering Supervisor

Phase 1 & 4.1 Contractor

Phase 2 Contractor

Phase 3 Contractor

Phase 4.2 Contractor

Phase 4.3 Contractor

Systems Contractor

long-term technical assistance